Please find following the latest construction progress update for The Prescott by Mosaic at 28 Lissner Street, Toowong, including any works that might impact you.
This month, Mosaic Construction will continue to progress with large concrete pours, targeting to achieve The Prescott's Level 3 and 4 pours, weather permitting.
Additionally, essential services such as water, sewer, and stormwater will be connected to site this month.
To facilitate this, there will be partial road and footpath closures to Lissner Street, with traffic control facilitating traffic and pedestrian movement.
I will be back in touch once we have firm dates for these works to be completed, ensuring you receive advance notice of any disruptions.
In the meantime, trucks will continue to move to and from site in line with our Traffic Management Plan, which is available for viewing on request.
Unless we notify you otherwise, all work will stay within our site hours, which are 6:30am to 6:30pm, Monday to Saturday.
Should you have any queries regarding the above, please do not hesitate to contact me via the below.
Thank you for your patience and understanding as we progress with construction activities.
If you are a Body Corporate in the Lissner Street area, we kindly ask that you please pass this information on to your building's occupants.
Kind regards,
|