Dear Valued Stakeholder,
I hope this finds you well.
Please find following the latest construction progress update for Cotton Tree by Mosaic at 17 The Esplanade and 62 Memorial Avenue, including any works that might impact you.
In recent months, while battling inclement weather, Mosaic Construction has persevered with basement works at the Memorial Avenue building and concrete slab preparation and pours at The Esplanade building.
The basement and residential-level concrete slab pours will continue throughout this month. Therefore, you will continue to see heavy trucks travelling to and from the site.
Per our approved traffic management plan (available for viewing on request), Mosaic Construction requires intermittent full road and partial lane closures in front of the site to facilitate these pours.
These periodic closures, essential for local community safety, will occur during site hours, which are 6:30am to 6:30pm, Monday through Saturday.
Traffic control will manage required traffic diversions for these closures, and access to neighbouring properties will always be maintained.
Mosaic Construction has obtained the required approvals and permits for the road closures from Sunshine Coast Council, which are also available for viewing on request.
We genuinely appreciate the temporary disruption these closures may cause. We appreciate your continued cooperation and understanding.
Should you have any queries regarding the above, please do not hesitate to contact me via the below.
If you are a Body Corporate in the Esplanade and Memorial Drive, Cotton Tree area we kindly ask that you please pass this information on to your building's occupants.
Kind regards,
|