Please find following the latest construction progress update for The Witton by Mosaic at 29 Finney Road, Indooroopilly, including any works that might impact you.
Following structural top-out at the Witton One (the large main building to the rear of the site) last month as planned, scaffolding will start to be progressively be removed towards the end of this month.
Concrete pours will also continue to Witton Two (the small building at the front of the site) throughout March, with the team targeting to achieve structural top out by month’s end, weather permitting.
Trucks will continue to move to and from site in line with our Traffic Management Plan, which is available for viewing on request.
Traffic control will remain in place during site hours to guide motorists, pedestrians, and cyclists and ensure their safety.
Unless we notify you otherwise, all work will stay within our site hours, which are 6:30am to 6:30pm, Monday to Saturday.
Thank you for your ongoing patience and understanding.
Should you have any queries relating to any of the the above, please do not hesitate to contact me via the below.
If you are a Body Corporate in the Finney Road, Indooroopilly area, we kindly ask that you please pass this information on to your building's occupants.